Sunday, October 4, 2009

Update on Construction

Hello everyone,
The weather has not been good to us. The rain has slowed down our subcontractor who is putting the footings, piers and foundation walls in. The footings, piers and foundation walls are concrete reinforced with steel that is basically placed in holes in the ground. When it rains the holes get filled with water and the soil turns to mud. It has caused the steel erection to be pushed back a week to October 12, 2009 instead of October 15,2009. Hope everyone is doing well. Terry