Hello everyone,
We started construction on Tuesday, September 15,2009(exactly 10 months after the fire). The first step is to pour "footings" which are the concrete pads which will support the steel reinforced concrete piers (all underground)that support the steel columns which will be what you see above ground. They will be pouring concrete all September to create these underground support structures.We are hoping the steel erection starts by the end of the month. It should take about three weeks to erect all the steel. We are looking at a tentative reopening date of April 1st for the entire facility. We hope to reopen Perkins/Legends before that but are still waiting on some information from the engineering firm before we can firm up that date more. I will post shorter more frequent updates now that something is actually happening. Best wishes to everyone. Terry